CONSTRUCTION UPDATE 

 

 New!  Construction Video November 2004
requires Windows Media Player 7 or better - this is a 10MB file
 
Previous Tours









October 2004
T
his summer was a busy one. Hundreds of construction workers labored long and hard at the five district construction sites rushing to complete classrooms to be ready for September's opening and bringing some major projects to "move in" condition. There were many "ohs and ahs" as teachers and students alike had a chance to walk through spanking-new facilities. Kevin Carpenter, in charge of the entire operation as Administrator of Facilities Operations, says that overseeing the development of this project "is probably the high light of his professional career." He expressed a well earned pride in the District's efforts dealing with the scope of this enormous undertaking and the positive results that have been achieved thus far.


 

 

 
BUILDING BY BUILDING DETAILS
Wood Park Primary School
bulletThe Phase I classroom addition consisting of six (6) classrooms has been completed, with new boys and girls bathrooms. The Phase II new four (4) classroom addition will be completed by mid-December.
bulletFoundations are finished.

Site Improvements:

bulletNew sanitary systems, sidewalks, curbs, and expanded bus areas.

Commack Middle School

bulletA new art room and technology addition consisting of three (3) art/technology rooms, one (1) graphic/computer room, one (1) general music room, four (4) ensemble rooms, and new boys and girls bathrooms have been completed and are in use.
bulletRenovations of existing classrooms complete: five (5) home and career rooms with cooking appliances such as, stoves, refrigerators, microwaves, dishwashers, tables and chairs are completed and in use.
bulletNew band rooms, orchestra room, instrument storage area, and chorus room completed and in use.
bulletFloor in existing gym refurbished.

Site Improvements:

bulletRenovation and expansion of existing nurse's area; added two (2) new toilets, conference room, testing and waiting area.
bulletRenovation of existing boys and gins locker rooms, showers, storage rooms with new ceramic tile floors, walls, locker bases and new lockers, lighting, and painted ceilings.
bulletThe new gymnasium (11,000 sq.ft.) with state of the art gym equipment will be ready by the end of the year.
bulletArea (F) two (2) story classroom addition foundations complete, steel is being erected.
bulletSanitary system under baseball field corrected.
Burr Intermediate School
bulletOne (1) classroom addition consisting of twelve (12) classrooms and 4,640 sq.ft. gymnasium are complete and occupied.
bulletCafeteria addition with new serving area and kitchen equipment completed.
bulletThree (3) new Science classrooms have been completed.
bulletOne (1) new Art Room has been added.
bulletNew bus turnaround with 39 additional parking spaces on the west side.
bulletReplaced all existing windows with new dual glazed double hung-windows.
Burr Intermediate School (cont.)

Site Improvements:

bulletNew sidewalks, curbs, entrance walkway, courtyard.
bulletRefurbished basketball courts.

Utility Improvements:

bulletNew boilers, pumps, sanitary systems, gas service, oil tanks and landscaping.

Sawmill Intermediate School

bulletOne (1) classroom addition consisting of six (6) classrooms is completed and occupied, with new boys and girls bathrooms, teacher's conference room, and storage room.
bulletNew 827 sq. ft cafeteria expansion.
bulletTwo (2) new art rooms.
bulletTwo (2) new science rooms.
bulletNew principal's conference room.
bulletUpgraded existing boys and girls bathrooms.

Site Improvements:

bulletExpanded west parking lot and added 13 new parking spaces in front of school building entrance, new side walks, curbs, and walkways.
bulletReplaced all existing windows.

Utility Improvements:

bulletNew boilers, pumps, fuel oil tanks, and sanitary systems.

Commack High School

bulletStairwell No. 2 is complete.
bulletNew parking lot on west side of building, presently being used by construction crew.
bulletNew band room will be complete January, 2005.
bulletRefurbished boys and girls locker rooms in north gym.
bulletNew two (2) story 40 classroom addition, steel erected, masonry begun, to be completed in fall of 2005.
 
    
We will be keeping you up-to-date on the latest developments on the Commack Website in the Community News section, and in future issues of the Commack Courier. For additional information, please contact Dr. James A. Feltman, Associate Superintendent for Operations at 912-2005.